01329 287 626

Plumbing Upgrades to a 12th Century Inn

We don’t believe in doing plumbing upgrades by halves - we investigate and rectify all possible problems so that the customer is assured it won’t happen again.

We don’t believe in doing plumbing upgrades by halves - we investigate and rectify all possible problems so that the customer is assured it won’t happen again.

If a hotel has water pressure in the showers, it’s likely an indicator of a bigger problem. One of our previous clients, The Bowl Inn in Almondsbury, was experiencing exactly that, as old buildings so often do. The Bowl Inn is a traditional pub and hotel, with history dating all the way back to the 12th century. For a long time, the electrical and plumbing efficiency, as well as the water pressure of the showers, had been neglected and suffered greatly for it. Hi-Tech Property Services were called in to help.

Plumbing Upgrades

To rectify the ongoing plumbing problems, we proposed a two-stage approach based on detailed flow rate and pipe sizing calculations;

The first stage focused on installing two 250-liter indirect cylinders in the plant room, heated by the existing Valiant EcoTech 65kW boiler. These cylinders were designated to form a dedicated shower circuit, ensuring the showers received an uninterrupted hot water supply. Concurrently, the existing top-floor cylinders were adjusted to provide hot water to the rest of the building. The pipework feeding the showers was resized to meet the required system flow rate, ensuring optimal water pressure and distribution.

The second stage involved extending the plant room to accommodate a booster set and tank with an MCWS bypass. This extension required either enlarging the current plant room or creating a temporary enclosure. The aim was to provide a balanced flow for the entire property, addressing any potential water pressure issues comprehensively.

Plumbing Upgrades

To rectify the ongoing plumbing problems, we proposed a two-stage approach based on detailed flow rate and pipe sizing calculations;

The first stage focused on installing two 250-liter indirect cylinders in the plant room, heated by the existing Valiant EcoTech 65kW boiler. These cylinders were designated to form a dedicated shower circuit, ensuring the showers received an uninterrupted hot water supply. Concurrently, the existing top-floor cylinders were adjusted to provide hot water to the rest of the building. The pipework feeding the showers was resized to meet the required system flow rate, ensuring optimal water pressure and distribution.

The second stage involved extending the plant room to accommodate a booster set and tank with an MCWS bypass. This extension required either enlarging the current plant room or creating a temporary enclosure. The aim was to provide a balanced flow for the entire property, addressing any potential water pressure issues comprehensively.

Electrical Support

The electrical works required were extensive, but critical for the successful completion of the plumbing upgrades. The immersion cylinder on the top floor, previously powered via contactors, was upgraded with silent switching SSRs installed within an enclosure. Additionally, two 13 amp power supplies were installed in the new plant room, each on a dedicated circuit to ensure reliable power delivery. Three FCUs were fitted in the plant room for fixed equipment, along with a dedicated FCU for the boiler supply. All this to ensure a stable power source for the new system components.

At maximum demand, a cold water flow rate of approximately 1.5 l/s was necessary. Given the improbability of achieving this flow rate at the cold water main, a practical approach was adopted. Instead of relying solely on theoretical demand calculations from BS6700 standards, the team implemented Stage 1 and planned for Stage 2 contingently. This pragmatic approach allowed for the assessment and adjustment based on actual usage patterns. This was to ensure the system could be scaled effectively if the demand warranted.

Electrical Support

The electrical works required were extensive, but critical for the successful completion of the plumbing upgrades. The immersion cylinder on the top floor, previously powered via contactors, was upgraded with silent switching SSRs installed within an enclosure. Additionally, two 13 amp power supplies were installed in the new plant room, each on a dedicated circuit to ensure reliable power delivery. Three FCUs were fitted in the plant room for fixed equipment, along with a dedicated FCU for the boiler supply. All this to ensure a stable power source for the new system components.

At maximum demand, a cold water flow rate of approximately 1.5 l/s was necessary. Given the improbability of achieving this flow rate at the cold water main, a practical approach was adopted. Instead of relying solely on theoretical demand calculations from BS6700 standards, the team implemented Stage 1 and planned for Stage 2 contingently. This pragmatic approach allowed for the assessment and adjustment based on actual usage patterns. This was to ensure the system could be scaled effectively if the demand warranted.

The plumbing upgrades to The Bowl Inn were executed with meticulous attention to detail and a clear strategy for future scalability. The project not only resolved the existing water pressure problems but also laid a solid foundation for future enhancements.

More Case Studies Like This One

See more below or click the button to view all our case studies.

Water pressure winstons southampton cs header

Water Pressure Problems Fixed First Time

Water pressure problems bothered the guests and staff on a regular basis at this busy Southampton venue, until we got there.

broken boiler case study cover

Broken Boiler - Repair vs Replace

What do you do when you’re given an extortionate quote for a brand new boiler? You call Hi-Tech for a repair instead!

Toilet refurbishment cs cover

Toilet Refurbishment and Upgrades at a Surrey College ​

Even high achievers need a pristine pit stop! Read about this full bathroom refurbishment. We designed everything!

Plumbing, Bespoke Joinery, Carpentry, Electrical Installation, Electronics.

Let’s start a conversation

Starting a new construction project, want more information on our PPM services, or perhaps just looking for a handyman for your commercial property?

Call 01329 287 626 7am – 5pm Monday – Friday for a conversation with someone straight away, or email us at
enquiries@hi-techproperties.co.uk 

Let’s start a conversation

Starting a new construction project, want more information on our PPM services, or perhaps just looking for a handyman for your commercial property?

Call 01329 287 626 7am – 5pm Monday – Friday for a conversation with someone straight away, or email us at enquiries@hi-techproperties.co.uk 

Let’s start a conversation

Starting a new construction project, want more information on our PPM services, or perhaps just looking for a handyman for your commercial property?

Call 01329 287 626 7am – 5pm Monday – Friday for a conversation with someone straight away, or email us at enquiries@hi-techproperties.co.uk