Fire Safety · Compliance · Electrical

Correcting the Coverage.

An issue spotted while our team was already on site led to a full review, redesign and upgrade of a fire alarm system that was not providing the protection required across a busy Southampton hospitality venue.

Environment Operational hospitality venue
Brief Correct inadequate fire alarm coverage
Scope Survey, design, installation, testing & commissioning
Delivery L3 fire alarm system brought back into compliance
Fire alarm equipment inspected during corrective works at a Southampton hospitality venue
The Brief

A problem noticed during another job became a life-safety project in its own right.

Our team was already completing minor refurbishment works at a busy Southampton hospitality venue when a project supervisor noticed that the existing fire alarm system had been wired using the wrong cabling and was not providing adequate coverage across the whole property.

Rather than treating it as somebody else’s problem, we arranged for one of our test engineers to inspect the installation. That review identified further departures from BS 5839 and confirmed that the existing system did not meet the requirements set out by the Fire Risk Assessment.

The latest Fire Risk Assessment required an L3 category system. Because building modifications were also taking place, the design first had to be checked against the proposed layout, signed off by the relevant stakeholders and coordinated with approved cable routes before installation began.

Problem identified Incorrect cabling and inadequate coverage spotted while our team was already on site.
System reviewed Testing identified additional departures from BS 5839 and Fire Risk Assessment requirements.
L3 design The revised system was designed around the category required by the latest Fire Risk Assessment.
Tested to completion Commissioning identified a final audibility issue, which was corrected before handover.
Design & Compliance

The Fire Risk Assessment set the requirement. The building shaped the solution.

The latest Fire Risk Assessment identified an L3 system as the required level of protection. The challenge was not simply to add devices, but to make sure the revised design worked with the building modifications already being completed elsewhere in the property.

The proposed design was coordinated with the refurbishment layout, agreed with the relevant stakeholders and reviewed internally before installation. Cable routes were also signed off by our Health & Safety Team so the corrective works could progress in a controlled and considered way.

Compliance is not achieved by assumption.

The system had to satisfy the required design category in the real building, and then prove that performance through testing and commissioning.

Fire alarm system equipment during corrective works
System Upgrade

The scope grew from testing, not guesswork.

The revised design required a substantial extension of the existing system. The installation included 23 additional smoke detectors, two additional heat detectors, 12 sounders, a remote indicator, a replacement panel with the correct number of zones and two door-hold devices.

Each element formed part of the same objective: make the fire alarm system match the protection required by the Fire Risk Assessment and provide appropriate coverage throughout the property. Installation was then followed by full testing rather than assuming that the design alone guaranteed the result.

That final testing proved essential. One bedroom did not achieve the required 75 dB sound level at the bedhead because a newly installed fire door sat between the room and the existing alarm device. The issue was reported, an additional device was instructed and the system was tested again.

23 additional smoke detectors
2 additional heat detectors
12 additional sounders
New correctly zoned fire alarm panel
Remote indicator & 2 door-hold devices
Completed bar refurbishment at the Southampton hospitality venue
Feature lighting installation at the Southampton hospitality venue
Refurbished interior at the Southampton hospitality venue
The Result

A system brought back into compliance — and properly proven.

What began as an observation during unrelated refurbishment works became a complete corrective fire alarm project. The original installation was reviewed, redesigned around the Fire Risk Assessment requirement and upgraded with the additional devices needed to provide the required level of protection.

Just as importantly, commissioning was used to prove the system in the finished property. When the sound-level test identified a problem in one bedroom, the project was not treated as complete until the additional device had been installed and the system had passed re-testing.

The customer was left with a compliant system and the corrective works were completed and handed over within the expected programme alongside the original refurbishment works.

Spot the problem. Design it properly. Test the result.
Services Used

Life-safety work carried through to completion.

Need a fire alarm system designed, upgraded or brought back into compliance?

From corrective works and system upgrades to new design, installation, testing and commissioning, talk to Hi-Tech about your commercial fire alarm requirements.

Start a Conversation →